Summary Plan

 

 
Home | Floating Structures | Risers and Moorings | Materials | Seafloor Engineering | Subsea Systems | Other Research | Site Map

Progress Reports: December 2005 June 2005 December 2004  June 2004   December 2003

Comparative Risk Analysis of Composite and Steel Production Risers for a Deepwater Floating Production System


OBJECTIVE:

As water depths increase, there is growing interest in the use of composite production risers instead of steel risers for deepwater production systems. The MMS’s Deepwater Operating Plan (DWOP) requires that new technology introduced in a deepwater development project must be shown to be as safe as existing technology. The project will compare the risks of a composite production riser for deepwater floating production systems with the risks of a steel riser that has the same functional requirements and service life, to demonstrate the safety of a composite riser relative to a steel riser.

APPROACH:

A Comparative Risk Analysis (CRA) will be conducted to compare the risks of composite and steel production risers. The specific riser functional requirements, service life, and configuration(s) for the composite riser will be based upon results from DeepStar Project 6120 on permitting composite risers, and will be subject to MMS approval. A configuration for a steel riser with the same functional and service requirements will be developed, and both will be designed in sufficient detail for analysis.

The Study Team will include expertise in the areas of risk analysis, deepwater production riser configuration and design, composite riser analysis, and steel riser analysis. The Study Team will interact with experts from industry, class societies, and regulatory authorities through a series of Workshops to (1) develop the riser systems for the CRA; (2) determine appropriate risk measures for this study; (3) identify hazards for the composite and steel riser, and the resulting consequences of failure; and (4) estimate the frequencies of such events.

The Study Team will use this information to estimate the risks for the composite and steel riser systems. Each riser system will be quantitatively analyzed to determine its responses to hazards and the resulting risks. Existing data will be sought to support the analyses. The resulting risks for the two riser systems will be compared to determine the risks of the composite riser relative to the steel riser. The study will be conducted such that the larger contributors to risk can be identified so that appropriate risk mitigation strategies and measures can be studied.

The Study Team will review intermediate results with the industry, class society, and regulatory experts at appropriate milestones to get their advice and input as the study progresses.

DEPLOYMENT OF RESULTS:

Results from this CRA study will be shared with the Workshop Participants as part of the study process, and will be documented in a Final Report that will be available to the MMS, other regulatory authorities, Workshop Participants, and the public. Results from this study could also provide a basis for
· Developing a process to qualify other new production or drilling risers,
· Developing any needed certification or testing requirements for composite risers
· Identifying NDE methods that could be useful in sensing the ongoing performance of composite risers during field service


ANTICIPATED PROJECT DURATION: 2 years
PROJECT PLAN FOR YEAR 1 (2003-2004):
Scope of Work:

The CRA for a composite riser configuration will be completed. The Study Team will
· Develop the functional requirements, service life, configuration, and design for the composite production riser
· Develop similar information for a steel riser with the same functional and service requirements
· Identify appropriate risk measures for the production risers
· Identify hazards and estimate the corresponding frequencies and consequences
· Complete a quantitative risk analysis for each riser system
· Compare the risks and identify potential mitigation strategies and methods as needed to manage risks
· Prepare a final report
The study will include a series of Workshops to interact with industry, class society, and regulatory experts as shown in Figure 1.

Figure 1 Workshop Process
Anticipated Results:

The Final Report will
1. Compare the risks for the specific composite production riser studied relative to an equivalent steel riser
2. Suggest strategies and methods to mitigate any risks as might be needed
3. Suggest NDE techniques that could be useful to monitor the insitu field performance of a composite riser

PROJECT PLAN FOR YEAR 2:

Scope of Work: This project could be continued to address
· Other composite production riser configurations
· Composite drilling risers
· Certification or testing requirements for composite risers
· Developing a process to qualify other new production or drilling risers
· Composite flowlines

Anticipated Results: To be determined depending on Scope

SPONSORSHIP: MMS
PRINCIPAL INVESTIGATOR (S) & OTHERS INVOLVED IN PROJECT: (see Figure 2 below)

PI(s): E. Ward, O. Ochoa, and R. Gilbert

Others: Dr. E.B. Denison (consultant), Dr. Ochoa’s graduate student, Riser designer/analyst(s) from Stress Engineering Services, Workshop Participants

Return to top


OTRC PROJECT STATUS REPORT

Date: December 2005

Project Title: Comparative Risk Analysis of Composite & Steel Production Risers

MMS Project: 490 TO Numbers: 73632/35985
PIs: E.G. Ward, O.A Ochoa, R. B. Gilbert (OTRC); C. Miller (Stress Engineering Services), E.B. Denison (Consultant)

COTR: S. Buffington

Estimated Completion Date: October 2005

Project Description: As water depths increase, there is growing interest in using composite production risers instead of steel risers for deepwater production systems. The MMS’s Deepwater Operating Plan (DWOP) requires that new technology introduced in a deepwater development project must be shown to be as safe as existing technology. The project compared the risks of a composite production riser (new technology) with the risks of a steel riser (existing technology) that has the same functional requirements and service life to demonstrate the safety of a composite riser relative to a steel riser for deepwater floating production systems. The Study Team included the expertise in composites, risk analysis, riser design & analysis, and riser operations & hardware from OTRC and industry.

Progress: The analyses of the steel riser had been completed in the previous year and those results are summarized in Table 1. The analyses of the composite liner have now been completed. Special attention had to be given to sizing the steel liner in the composite tube. Global analyses of the riser response had been completed, and were used as input to the more detailed analyses of the composite riser, consisting of the composite tube and the steel liner. The composite tube was analyzed at the fiber and matrix level. The analyses included load cases that addressed:
• maximum combined axial tension and bending moments
• burst
• collapse (buckling)
• fatigue
Results were documented in a report by W. Kim (see below) and are summarized in Table 2.
Thermal effects on the composite riser were addressed by looking at an extreme case that could happen during well start-up. Assume that the annulus was filled with brine, a good conductor, and the initial temperature was 40F (the ambient water temperature at the seafloor). After start-up, heat from the produced fluids (180F) could rapidly heat up the tubing, annular fluid, and liner to 180F. Meanwhile the composite tube remained at near ambient temperature, was a perfect insulator, and did not expand. The thermally induced stress in the tubing would be 26 ksi, well below yield and thus not be a concern. The impact on the tubing string was also examined. Assuming the 5 ½ inch tubing was axially constrained at the surface and below the mudline (via a hanger), the heating and resulting expansion of the tubing after starting up the well could result in a stress reduction of 23 ksi and a tension reduction of 150 kips. Depending on the residual tension when the riser was installed, this expansion could result in compression at the mudline and helical buckling, but the tubing would not yield due to the modest compressive stress. This tubing performance would be similar to that experience in insulated steel risers that are currently used in deep water. Comparing Tables 1 and 2, we conclude that both the steel and composite risers can meet the prescribed design and operational requirements. The Final Report documenting this comprehensive comparative risk analysis of a steel and composite production riser is being completed and should be available for review by April 1. Reports & Publications: Risk Analysis of Steel Production Risers for Deepwater Offshore Facilities (2004), thesis by Anubhav Jain under the supervision of R.M. Gilbert, University of Texas, December Structural Response of Composite Production Risers (2005), W. K. Kim, O. O. Ochoa, E. G. Ward, & C. A. Miller, paper at Fourth International Conference On Composite Materials for Offshore Operations, Houston, TX, October 4-6, 2005. Comparative Risk Analysis of Composite and Steel Production Risers: Composite Riser Response Assessment (2005), report by Won K. Kim & Dr. Ozden Ochoa, Texas A&M University, December

Table 1.  Steel Riser

Hazard

Failure Mode

Allowable/    Design Target

Predicted Performance

Minimum Failure

Risk

Remarks

Kick control while drilling

Burst

8500 psi

8500 psi (60% of calculated minimum burst)

14,170 psi (minimum burst)

Loss of pressure containment

API RP-1111 Calculation, 12.5% mill tolerance, 0.050" corrosion and wear allowance.

Tubing leak

Riser evacuation

Collapse

6,000 ft WD      (2,660 psi)

2,660 psi         (6,000 ft WD)

12,680 psi

API 5C3 Calculation, elastic collapse, using nominal wall.

Excessive riser axial stress

Axial yielding

64 ksi

(80% yield)

Max above SJ is 52 ksi, max below TJ is 30 ksi    (see Note 1)

80 ksi (yield)

Loss of pressure containment, parted riser

100-year Hurricane, API RP 2RD

Max above SJ is 60 ksi, max below TJ is 32 ksi    (see Note 1)

100-year Loop current, API RP 2RD

Wave fatigue

Crack, parting

Minimum life = 200 years

Variable damage, minimum life of 200 years (see Note 2)

Cumulative Damage = 1.00 or calculated life = 20 years or less

Damage calculations for 20 year life with factor of 10 for non-inspectable components.  VIV fatigue mitigated by suppression equipment.

VIV fatigue

No damage

Dropped objects

Denting, leakage in connector

     

Loss of pressure containment

This is typically not evaluated for riser systems.  Tests have shown the joints and connectors to be robust.  No information exists on riser joints that have been damaged in service by external collisions or dropped objects.

Riser-to-riser collisions

Note 1:The stress joint above the seabed and the tensioner joint just above the sea surface are specialty joints that have not been carefully designed and analyzed for this study.  Results are emphasized here for the riser joints only.  The stress in the middle portion of the riser is lower than at the two extremes noted in the table.

Note 2: Analyses show that with the normal practice of using forged steel stress joints and tensioner joints, achieving the required fatigue performance in the stress joint and tensioner joint are not a problem.  Results indicate that the riser joint welds must be ground to achieve DNV C-curve performance for the first 200 ft above the stress joint.  Above these few joints, unground welds meeting the DNV F2 curve will achieve the needed fatigue life.

Table 2.  Composite Riser

Hazard

Failure Mode

Allowable/    Design Target

Predicted Performance

Minimum Failure

 

Remarks

Kick control while drilling

Burst

8500 psi

11,000 liner yield, body is significantly stronger

18,000 psi matrix yield, 30,000 psi fiber limit

Loss of pressure containment

 

Tubing leak

Riser evacuation

Collapse

6,000 ft WD      (2,660 psi)

12,400 psi

 (leak in outer liner, complete debonding of steel liner)

12,400 psi w/ debonded liner 29,400 psi w/ limited debonding

With no breach of outer structure, riser is stronger than the 29,400 psi figure.

Excessive riser axial stress

Axial yielding of liner

64 ksi

 (80% yield)

Max at Top of Composite Riser (74 ft WD) is 31 ksi (Note 3)

80 ksi (yield)

100-year Hurricane, API RP 2RD, riser will remain intact even with yielded liner.

Max at Top of Composite Riser (74 ft WD) is 23 ksi (Note 3)

100-year Loop current, API RP 2RD, riser will remain intact even with yielded liner.

Wave fatigue

Crack, parting of liner

Minimum life = 200 years

Minimum life is 80,000 years (Composite Section)

Cumulative Damage = 1.00 or calculated life = 20 years or less

Results for composite riser section only (see Note 3).  Steel sections (top & bottom) designed using normal practices for all-steel risers. Damage calculations for 20 year life of liner welds with factor of 10 for non-inspectable components using DNV E curve for unground welds.  No need for ground welds in composite joints.  VIV fatigue mitigated by suppression equipment. Composite body has much longer predicted life. 

VIV fatigue

No damage

Dropped objects

Denting, leakage in connector

     

Magnolia riser joints impact tested to 10 MJ.

Riser-to-riser collisions

Note 3: Composite riser section is between 102 ft, (54 ft above SJ) to 5926 ft (124 ft below bottom of TJ & 74 ft below MWL. The max composite joint liner stress is near the surface rather than near the stress joint above the seabed.  The composite structure is much stronger than the liner.

Return to top

OTRC PROJECT STATUS REPORT

Date: June 2005

Project Title: Comparative Risk Analysis of Composite & Steel Production Risers

MMS Project: 490 TO Numbers: 73632/35985

PI: E.G. Ward, O.A Ochoa, R. B. Gilbert (OTRC); C. Miller, E.B. Denison (industry)

COTR: Andrew Konczvald

Estimated Completion Date: October 2005

Project Description: As water depths increase, there is growing interest in using composite production risers instead of steel risers for deepwater production systems. The MMS’s Deepwater Operating Plan (DWOP) requires that new technology introduced in a deepwater development project must be shown to be as safe as existing technology. The project will compare the risks of a composite production riser (new technology) with the risks of a steel riser (existing technology) that has the same functional requirements and service life to demonstrate the safety of a composite riser relative to a steel riser for deepwater floating production systems. The Study Team includes the expertise in composites, risk analysis, riser design & analysis, and riser operations & hardware from OTRC and industry.

Progress: The comparative failure modes for steel and composite risers have been considered. Failure for the steel riser has been defined as a through-wall crack that leads to a leak or riser failure. Failure modes for the composite riser are very different. The composite riser depends upon the steel liner and the outer elastomeric layer for pressure containment since the composite tube itself will weep. A crack in the liner can lead to a loss of pressure containment. A hole in the outer elastomeric covering could lead to external pressure on the liner causing a collapse and perhaps even a crack that would result in loss of pressure containment. Continuing research focused on the composite riser. Further study of the steel liner for the composite riser focused on the girth welds of the liner. The liner thickness for the study riser was increased to mitigate concerns regarding undetectable weld flaws that could lead to through-wall cracks, and the study riser was resized. Global riser analyses were completed to predict the composite riser responses under a variety of important design cases, including 100-year hurricane conditions, 100-year loop current conditions, and the 1-year winter storm case. The computed distributions of tensions and bending moments are being used as the basis and boundary conditions for detailed local analyses of the composite tube. These local analyses will investigate the expected amount of fiber failure and matrix cracking in layers of the composite tubular under different loading conditions. These analyses will be used to examine the likelihood and degree of failure in the layers of the composite tubular, and the remaining strength of the riser.

Reports & Publications: Risk Analysis of Steel Production Risers for Deepwater Offshore Facilities (2004), thesis by Anubhav Jain under the supervision of R.M. Gilbert, University of Texas, December. Return to top


OTRC PROJECT STATUS REPORT

Date: December, 2004

Project Title: Comparative Risk Analysis of Composite & Steel Production Risers

MMS Project: 490 TO Numbers: 73632/35985

PI: E.G. Ward, O.A Ochoa, R. B. Gilbert (OTRC); C. Miller, E.B. Denison (industry)

COTR: Julie McNeil

Estimated Completion Date: July 2005

Project Description: As water depths increase, there is growing interest in using composite production risers instead of steel risers for deepwater production systems. The MMS’s Deepwater Operating Plan (DWOP) requires that new technology introduced in a deepwater development project must be shown to be as safe as existing technology. The project will compare the risks of a composite production riser (new technology) with the risks of a steel riser (existing technology) that has the same functional requirements and service life to demonstrate the safety of a composite riser relative to a steel riser for deepwater floating production systems. The Study Team includes the expertise in composites, risk analysis, riser design & analysis, and riser operations & hardware from OTRC and industry.

Progress: Preliminary analyses of the steel riser design being used for this study were completed. These analyses included global analyses to predict the overall response of the risers to various storm and operational conditions that represented the design load cases. Analyses of riser responses under operational conditions were also completed to define the long term fatigue loading on the riser. A risk analysis of the steel riser was completed to develop the methodology and framework to compare the risks of steel versus composite production risers, and provide preliminary results for the steel riser. Failure was defined as a through wall crack, and the risks of a through wall crack developing during the design life were evaluated for a number load scenarios including burst(kick, production tubing leak), collapse (hydrostatic pressure), yield (high tension or compression, dropped objects), and fatigue (wave loading – it was assumed that VIV could be suppressed through strakes). The results are reasonable for the steel riser. The steel liner for the composite riser was further studied and focused on the girth welds of the liner. Concerns centered on the ability to sizes of flaws in the weld that could be detected versus the size of a flaw that could lead to through wall cracks during the design life. A preliminary wall thickness was selected for further study. The composite riser was resized for this liner thickness, and sectional properties were developed and used to complete preliminary global analyses. Failure modes for the composite riser continued to be studied along with detailed analyses of the composite riser under various loading scenarios.

Reports & Publications: Risk Analysis of Steel Production Risers for Deepwater Offshore Facilities (2004), thesis by Anubhav Jain under the supervision of R.M. Gilbert, University of Texas, December

Return to top


OTRC PROJECT STATUS REPORT

Date: June 2004

Project Name: Comparative Risk Analysis of Composite and Steel Production Risers for a Deepwater Floating Production System

Project Number: 490 Task Order: 73632

Principal Investigators: E.G. Ward, O.A Ochoa, R. B. Gilbert (OTRC); C. Miller, E.B. Denison (industry)

Estimated Completion Date: July 2005

Project Description: As water depths increase, there is growing interest in using composite production risers instead of steel risers for deepwater production systems. The MMS’s Deepwater Operating Plan (DWOP) requires that new technology introduced in a deepwater development project must be shown to be as safe as existing technology. The project will compare the risks of a composite production riser (new technology) with the risks of a steel riser (existing technology) that has the same functional requirements and service life to demonstrate the safety of a composite riser relative to a steel riser for deepwater floating production systems. The Study Team includes the expertise in composites, risk analysis, riser design & analysis, and riser operations & hardware from OTRC and industry.

Progress: The functional requirements and design parameters for the risers have been established. The riser will be a single-casing production riser for a TLP in 6000 ft. Workover operations will be conducted through the riser. A standard steel riser is being used for the study. A “design” for the composite riser has been completed. Properties of the composite materials (fiber and matrix) and the stacking sequence have been established from available literature. Containment capabilities of steel and production risers are quite different, and considerable effort has been focused on developing a composite riser design that is sufficient to capture these differences and serve as a basis for comparing the risks without becoming too detailed (as in a specific final design). A riser with a steel liner, composite body, rubber barrier, and epoxy coating will be studied. The bottom stress joint and the tensioner and first riser joint (to below the water line) will be steel for the composite riser. The analyses and the load cases have selected. The hurricane and loop current environments are being specified, and the cases have been developed and planned. Containment capabilities of steel and production risers are quite different, and considerable effort has been focused on developing a composite riser design for this study that is sufficient to capture these differences and serve as a basis for comparing the risks without becoming too detailed (as in a specific final design).
The analyses of both the steel and composite risers have been initiated. Load cases have been selected for comparing the risks. Planning for the comparative risk analyses is nearing completion.
We have consulted with industry in developing some of study parameters and assumptions. In the next Quarter, we will invite industry and class society experts to a meeting to review the study progress and provide feedback.

Reports & Publications: None Return to top


OTRC PROJECT STATUS REPORT

Date: December 2003

Project Name: Comparative Risk Analysis of Composite and Steel Production Risers for a Deepwater Floating Production System

TEES Project Number: 32558-60280

MMS Task Order: 73632 MMS Project Number: 490

Principal Investigators: O.A Ochoa, R. B. Gilbert, E.G. Ward

Estimated Completion Date: May 2003

Project Description: As water depths increase, there is growing interest in the use of composite production risers instead of steel risers for deepwater production systems. The MMS’s Deepwater Operating Plan (DWOP) requires that new technology introduced in a deepwater development project must be shown to be as safe as existing technology. The project will compare the risks of a composite production riser for deepwater floating production systems with the risks of a steel riser that has the same functional requirements and service life, to demonstrate the safety of a composite riser relative to a steel riser and the use of Comparative Risk Analysis to demonstrate the safety of new technology.

Progress: A plan and a Study Team have been developed. A Study Team combining the talents and experience of OTRC faculty and industry experts has been set up:
o Composite riser analysis – O.A. Ochoa (Texas A&M)
o Risk analysis – R.B. Gilbert (U. Texas)
o Steel riser design & analysis – C. Miller (Stress Engineering)
o Production riser operations & hardware – E.B. Denison (consultant)
The Study Team will proceed to:
o Obtain the functional & service requirements, configuration, and design for the composite production riser from industry sources
o Develop similar information for a steel riser with the same functional and service requirements
o Identify appropriate risk measures for the production risers
o Identify hazards and estimate the corresponding frequencies and consequences
o Complete a quantitative risk analysis for each riser system
o Compare the risks and identify potential mitigation strategies and methods as needed to manage risks
The study will include a series of Workshops to interact with industry, class societies, and the MMS to gather information and review progress.
Information on the composite riser is being compiled, and the OTRC faculty has initiated studies on riser mechanics and the application of risk analysis methodologies to risers.

Reports & Publications: None

Return to top